Page 54 DRI-STEEM GTS Humidifier Installation, Operation, and Maintenance Manual
5. Verify that the humidifier tank is securely installed and level
before filling with water (see the operating weights table in this
manual).
6. Verify that the humidifier tank is level front to back and side to
side after it is full of water.
7. Refer to the following sections in the Vapor-logic4 Installation
and Operation Manual:
Operation section
Start-up checklist (it is critical that the installer follow this
checklist)
8. During start-up, do not leave the humidifier unattended.
9. Monitor humidifier operation through multiple fill cycles. The
humidifier operating status appears on the keypad/display.
10. On standard water units, water skims from the humidifier
after every fill cycle. Adjust the amount of skim by increasing
or decreasing the skim time (see the Vapor‑logic4 Installation
and Operation Manual). However, at start-up, DRI-STEEM
recommends initially running the humidifier with the factory
default setting for skim time. (See "Adjusting skim duration" in
the maintenance section of this manual, and see the
Vapor-logic4 Setup menu.)
S t a r t - u p p r o c e d u r e ( c o n t i n u e d )